For the past several decades LEONHARD WEISS has proven to be a leader in high-quality installation of underground cables. We employ the latest installation technology and a highly skilled staff to provide you with unparalleled service. The scope of our services encompasses low voltage to 380 kV high voltage cables, and from domestic phone connections to main cables with 2,000 twisted pairs.
Our services:
Cable installation work for power cables of up to 380 kV, cable installation work for all telecommunications and data transmission cables, cable installation work in substations, removal and disposal of oil-filled cables.

|
Customer: Jakob Gärtner, on behalf of Stadtwerke Worms
Construction time: October 2008
Facts and figures:
110-kV cable installation from the Rosengarten substation through the Rhine culvert to the Alegro company.
Route length approximately 8,000 metres.
Customer: EnBW Regional AG
Construction time: March – September 2010
Facts and figures:
Cable installation, 110-kV/1200 square metres, from Münster power station to the Seewiesen substation.
Route length approximately 4,000 metres.
Customer: Südkabel GmbH, on behalf of EnBW
Construction time: March 2010
Facts and figures:
Cable installation, 110-KV, medium and low voltage cables, telephone cables.
Rhine Power Plant, Iffezheim through the Rhine culvert to the substation.
Cable length, approximately 16 kilometres.
Customer: Südkabel GmbH, on behalf of Stadtwerke Pforzheim
Construction time: April 2010
Facts and figures:
110-kV cable installation from the Enzwerk substation to the Rennfeld substation.
Route length, 3,000 metres.
Customer: Nexans, on behalf of Stadtwerke Würzburg
Construction time: September 2010
Facts and figures:
110-kV cable installation from the Greinberg substation to the Dürrbachau substation.
Route length, 7,000 metres
Customer: Südkabel, on behalf of EnBW Regional AG
Construction time: 2009/2010
Facts and figures:
110-kV, 1,600 square metres cable installation in the Grossgartach substation. Cable length approximately 1,000 metres.
Cable installation, 110-kV/1,000 square metres, from Grossgartach power station to the cable end mast. Cable length approximately 2,000 metres.
|
|