Runways, aprons and taxiways. |
Airport renovation within 15 days in 24-hour shifts
Customer: Flughafen Niederrhein GmbH, Weeze-Laarbruch
Construction time: 2007 (15 days, 24-hour construction site)
Facts and figures:
- Expansion to CAT II / III - Repair of the south taxiway
- Complete reconstruction of a large part of the existing airport surface
- Renovation of 900 m of runway (30 m wide)
- Renovation of the 15 m wide taxiways with an overall length of 2,900 m
- Laying of vacant duct routes including cable shafts and edge lighting foundations
- Execution of the work during the day and night shifts
- Simultaneous use of 8 asphalting teams up to 7 road building teams
- Concrete demolition: 45,000 square metres
- Concrete demolition: 27,000 square metres
- Cement solidification with concrete recycling: 45,000 square metres
- Asphalt installation: 43,000 t
- Cable protection pipes with 50 cable shafts: 12,000 m
Complete airport renovation with ongoing operations
Customer: Baden Airpark, Rheinmünster
Construction time: 18 months
Construction year: 2008 – 2009
Facts and figures:
Expansion and renovation of the airport surfacing of the Karlsruhe Baden-Baden airport on an area of 450,000 square metres. Renovation and lighting of the existing runway for CAT III flight operations.
- New construction of a parallel runway, connection taxiways, aprons and associated taxiways
- Construction of new south and north de-icing areas
- Civil engineering work for technical equipment
- Landscaping work
- Marking work
- Earth moving: 135,000 cubic metres
- Drainage pipes to DN 2200: 15,000 m
- Cable protection pipe routes: 67,000 m
- Slotted channel, class F 900: 12,000 m
- Frost protection layer 0/45: 150,000 t
- Concrete and asphalt surface removal, preparation and reinstallation: 85,000 t
- Asphalt: 300,000 t
Regional airfield
Customer: Staatliches Hochbauamt Schwäbisch Hall
Construction time: 20 months
Construction year: 2009 - 2010
Facts and figures:
- Replacement of the entire lighting system
- Storage area with helicopter landing area, approximately 25,500 square metres of concrete traffic surfaces
- Asphalt (taxiways), approximately 4,500 square metres
- Security patrols, around 43,000 m
- Gravel and grass surfaces of approximately 63,000 square metres

American planes can land again
Customer: Staatliches Bauamt Nürnberg
Construction time: 7 months
Construction year: 2010
Facts and figures:
- Renovation of the runway over an area of 40,000 square metres
- Installation of 47 cm of gravel
- 14 cm asphalt base and 4 cm of asphalt surface
- Removal of old lights and creation of the new lighting system
- Creation of a new drainage system (2 km)

|
|