Road building

Quick introduction

Find out quickly and comfortably about the range of services offered by LEONHARD WEISS BAUUNTERNEHMUNG. Our “Quick introduction” will give you an overview of our entire product portfolio.

Our services:
Federal, provincial and municipal roads, bypasses/urban links, footpaths and cycle tracks Country and forestry routes

Expansion of Heininger Straße L 1217

Excavation and road construction

Customer: Stadt Göppingen
Construction time: 6 months
Construction year: 2011

Facts and figures:
- Shortening of the construction period by 2.5 months (before school holidays)
- Preparation and utilisation of 4,000 t of broken concrete
- Installation of 7,500 t of asphalt

 

 

 

B 10 surface renovation between Oberesslingen and Mettingen

Surface renovation and installation of noise-optimised stone mastic asphalt

Customer: Regierungspräsidium Stuttgart, Dienstsitz Göppingen
Construction time: 6 weeks
Construction year: 2011

Facts and figures:
Construction implementation within a consortium – 50 % share

Implementation of construction work in four primary construction phases with dynamic traffic guidance 2 + 1 or 1 +2 on construction length of 6,000 m.
Installation of 15,000 t of asphalt top coat course, 110,000 m² of asphalt binder and 110,000 m² of sound-optimised stone mastic asphalt.
Renovation of a bridge structure in two-shift operation.

 

 

 

Expansion and construction of the western bypass of Schwäbisch Hall

The biggest project in the region of Schwäbisch Hall

Customer: Landratsamt Schwäbisch Hall
Construction time: 36 months
Construction year: 2008 – 2011

Facts and figures:
- Expansion and new construction of K 2576 over a length of 7.6 km in three construction stages
- Connection to the existing B 14 west of Schwäbisch Hall
- Connection to the existing B 19 north of Untermünkheim
- Connection of K 2576 to the motorway feeder to federal motorway A 6
- Construction of 13 bridges
- Restoration of 2.5 km of road
- Delivery and installation of bulk materials: 413,265 t
- Production and improvement of the base grade: 86,250 m²
- Loosening and installation of soil class 3-7
- Delivery and installation of asphalt: 260,000 t
- Drainage line production: 7,520 m
- Delivery and production of district heating lines: 1,700 m

 

 

 

Schlossberg infrastructure in Heidenheim

New routes to the Congress Centrum

Customer: Stadt Heidenheim
Construction time: 18 months
Construction year: 2008 – 2009

Facts and figures:
Expansion and conversion of the outdoor theatre forecourt and creation of a roundabout at the Congress Centrum in Heidenheim.

- Excavation: 15,500 cubic metres
- Asphalt base: 12,000 square metres
- Asphalt covering layer: 16,300 square metres
- Paving stones: 2,800 m
- Concrete paving stones: 1,800 square metres
- Installation with 3 pavers

 

 

 

B 469 Obernburg

Noise reduction by overlay of porous asphalt (OPA)

Customer: Staatliches Bauamt Aschaffenburg
Construction time: 4 months
Construction year: 2009

Facts and figures:
The works were divided into four construction phases, each with a length of approximately 3,000 m. The asphalt binder course was renewed before the "OPA" was installed.

- Asphalt milling of approximately 64,500 square metres
- of porous asphalt PA 8 (OPA), approximately 68,500 square metres

 

 

 

Roadway renovation, B 466 in Heidenheim

Free drive into the Heidenheim Oststadt

Customer: Regierungspräsidium Stuttgart, Dienstsitz Ellwangen und Stadt Heidenheim
Construction time: 12 months
Construction year: 2009 - 2010

Facts and figures:
Renovation of groundwater basin and the creation of a roundabout on the B 466 in Heidenheim.

- Asphalt binder: 9,000 square metres
- Asphalt base: 10,700 square metres
- Asphalt covering layer: 16,250 square metres
- Paving stones, 2,900 m
- Sealing work and poured asphalt protective layer: 2,800 square metres
- Granite cobble stone surface: 1,000 square metres

 

 

 

B 19 local bypass, Gaisbach

A main road of national importance

Customer: Regierungspräsidium Stuttgart
Construction time: 18 months
Construction year: 2009-2010

Facts and figures:
- 3.3 km of main road
- 2 km of country roads
- Just under 4 km of cycle tracks and footpaths

There were also two bridge structures, a storm water basin and retention ponds, a reinforced concrete retaining wall and a 300-metre long and up to 5 m high gabion wall.

Excavators, bulldozers and dumper trucks moved a total of approximately 120,000 cubic metres of earth.

 

 

 

Neckartalstrasse L 1100 in Heilbronn

Full development with traffic

Customer: City of Heilbronn
Construction time: 15 months
Construction year: 2008 – 2010

Facts and figures:
Expansion and conversion of several very busy junctions while maintaining traffic (approximately 20,000 vehicles per day).

- Upgrading of the L 1100 "Neckartalstrasse" over approximately 500 m from 2 to 4 lanes, plus turning lanes
- Upgrading of one lane of the K 9560 "Wimpfener Strasse"
- Replacement of the top layers

All links to existing roads had be created at night owing to high levels of traffic.
- Earthworks: 26,000 cubic metres
- Asphalt: 30,000 square metres