Sewerage systems and canalisation

Quick introduction

Find out quickly and comfortably about the range of services offered by LEONHARD WEISS BAUUNTERNEHMUNG. Our “Quick introduction” will give you an overview of our entire product portfolio.

Our services:
Residential areas, commercial and industrial areas, logistics centres.

Connection of the old Göppingen Weber area

Consideration of nature conservation

Customer: Möbel Rieger Objekt GmbH & Co. KG, Göppingen
Construction time: 4 months
Construction year: 2011

Facts and figures:
- Interruption by "sand lizards" of approx. four weeks and creation of compensation areas, as well
  as the capture and relocation of the lizards.
- Installation of 24,000 t broken material
- 1,210 m reinforced concrete sewerage DN 300 to DN 700

 

 

 

New construction of Rhine Neckar Arena in Sinsheim

LEONHARD WEISS is building for the Bundesliga

Customer: DH Besitzgesellschaft mbH & Co. KG, Walldorf
Construction time: 20 months
Construction year: 2007 - 2008

Facts and figures:
- Stadium for 30,000 spectators
- Road construction, earthworks, drainage for the indoor and outdoor facilities
- Topsoil removal: 55,000 cubic metres
- Soil removal and installation of: 237,000 cubic metres
- Drainage for outdoor facilities DN 250 PVC - DN 1400
- Reinforced concrete: 3,200 m
- Building drainage, DN 100-DN 500 PVC: 1,500 m

 

 

 

A 6 autobahn, Sinsheim-Süd

Pedestrian underpasses constructed with corrugated steel profiles

Customer: Regierungspräsidium Karlsruhe, Dienstsitz Heidelberg
Construction time: 2 months
Construction year: 2008

Facts and figures:
Part of the overall Sinsheim-Süd autobahn project.
2 underpasses were created, to provide an uninterrupted traffic flow from Sinsheim to the Rhein Neckar Arena and the Sinsheim Messe car parks.

 

 

 

Sewerage system of Ulmenweg in Dettingen

New residential area in the Swabian Alb

Customer: Municipality of Gerstetten
Construction time 8 months
Construction year: 2008

Facts and figures:
- Excavation: 2,500 cubic metres
- Asphalt base 2,500 square metres
- Duct trench excavation, 6,300 cubic metres
- Pipe trench excavation: 2,000 cubic metres
- Granite paving stones in one or two lines: 1,300 m
- Shafts, DN 1000 - 1500: 51 pieces
- Reinforced concrete pipes, DN 300 - 800: 750 m
- Plastic pipes, KG 2000 DN 250: 650 m

 

 

 

Sewerage system of "Äussere Helde" residential area in Wiesloch

Space for living

Customer: Stadt Wiesloch
Construction time: 11 months
Construction year: 2008

Facts and figures:
- Total surface area 17.4 ha with 17,000 cubic metres of earthworks
- Pipeline construction in the modified mixing system, 3,800 m
- Storm water retention basin as an engineering construction, including mechanical and electrical engineering
- Storm water retention basin in ground basin form
- Water pipe construction, 2,900 m
- 2,300 m of district heating network
- Cable laying work, 6,300 m
- 4,000 m of asphalt paving

Road construction:
- Paving stone fitting, 5,800 square metres
- Tongue-and-groove system, 3,200 m
- Rural road construction, 2,000 square metres

 

 

 

Sewerage system of the Sinsheim-Süd industrial area

Huge earth moving operations for new industrial facilities

Customer: MVV Energiedienstleistungen GmbH REGIOPLAN, Mannheim
Construction time: 18 months
Construction year: 2008 - 2010

Facts and figures:
New industrial area to the west of the Rhein Neckar Arena (TSG Hoffenheim 1899), accessible via the new Sinsheim Süd autobahn junction (A 6 autobahn). Extensive terrain modelling on an area of 41.9 ha for the creation of large, flat surfaces.

- Construction of a rainwater clarifier and water retention basin
- Topsoil removal: 123,000 cubic metres
- Topsoil cover: 83,000 cubic metres
- Soil removal and installation of: 80,000 cubic metres
- Soil removal, loading and disposal: 470,000 cubic metres
- Soil improvement: 8,400 t
- Water pipes, 100-300 DN: 2,700 m
- Ballast: 12,800 square metres
- Asphalt installation: 10,400 square metres
- Paving: 2,420 square metres

 

 

 

Pressure sewer in Gerstetten

Completion of the pressure sewer that is currently Germany's longest

Customer: Municipality of Gerstetten
Construction time 9 months
Construction year: 2010 - 2011

Facts and figures:
Creation of a pressure sewer with a length of 42.5 km, from Gerstetten to the municipal sewage treatment plant at Mergelstetten.
- Line trenches for sewage discharge pipe, length = 18,000 m; depth = 1.50 - 6.50 m
- Waste water pressure pipes, DN 140-315; length = 42,500 m
- Water pipe, DN 150; length 2,300 m
- 34 manholes
- 11 throughpress systems