Waste disposal sites

Quick introduction

Find out quickly and comfortably about the range of services offered by LEONHARD WEISS BAUUNTERNEHMUNG. Our “Quick introduction” will give you an overview of our entire product portfolio.

Our services:
Waste disposal sites, earth waste disposal sites.

Waste disposal site renovation at Kanzhalde in Wernau

Civil engineering and earthworks on the waste disposal site

Customer: Stadt Wernau
Construction time: 5 months
Construction year: 2006

Facts and figures:
9-10 m deep DN 250 drainage pipes were fed into a pre-perforated DN 500 reinforced concrete duct. The construction pit for the 9-10 well shafts was produced with glide rails. Drainage gravel and lime deficient gravel were used as filler. The excavated waste was only partially used and had to be deposited elsewhere at the waste disposal site.

 

 

 

Sinsheim waste site

Completion of the 1st Waste disposal site section

Customer: AVR Abfallverwertungsgesellschaft des Rhein-Neckar-Kreises mbH
Construction time: 6 months
Construction year: 2009

Facts and figures:
Expansion of the existing sorting plant to include a container storage area and a bale warehouse for recyclables. The construction of a surface sealing system in the form of a TASI control system above waste disposal site section I for waste disposal site class II

- Road widening with waste disposal site asphalt
- Work on the existing gas system
- In-situ concrete floor slab: 2,600 square metres
- asphalt base and asphalt concrete (acid resistant): 1,400 square metres
- Earthworks: 15,000 cubic metres
- Profiling material: 30,000 cubic metres
- Mineral sealing: 15,000 cubic metres
- Plastic seal track and protective fleece: 30,000 square metres
- Deep gravel: 17,000 t
- Filter gravel: 30,000 square metres
- Recultivation soil: 30,000 cubic metres
- Waste disposal site asphalt: 1,500 square metres

 

 

 

Plateau at Schwäbisch Hall – Solpark

New waste disposal site for the district

Customer: Stadt Schwäbisch Hall
Construction time: 3 months
Construction year: 2008 - 2011

Facts and figures:
- Delivery of earth material up to Z 1.2
- Total volume: 150,000 cubic metres
- Profiling work: 40,000 square metres