Bridge renovation on the A 81 autobahn, Osterburken

Customer: Regierungspräsidium Stuttgart DS Heilbronn
Construction time: 17 months
Construction year: August 2009 – December 2010

Facts and figures:
5 bridges (3 overpasses, 2 underpasses)
Asphalt surface: 1,500 square metres
Poured asphalt: 150 t
Surfacing concrete: 200 cubic metres
Surface structure coating: 850 square metres
Grouting of cracks: 250 m
BW drainage: 200 m

 

 

 

N 1 / N 7, Winterthur / Schweiz

Customer: Bundesamt für Strassen in der Schweiz ASTRA
Construction time: 3 years, approximately 8 months each year
Construction year: 2009 – 2011

Facts and figures:
Line length: 20 km
Structures: 13 overpasses
21 underpasses
Largest single project in Switzerland
Poured asphalt: 3,500 t
Sealing surface: 8,500 square metres

 

 

 

A 7 autobahn, BW 728b Pfeffermühle viaduct (Würzburg – Ulm)

Customer: Autobahndirektion Nordbayern DS Würzburg
Construction time: 3.5 months
Construction year April – July 2009

Facts and figures:
Bridge length: 410 m
Bridge width: 14.50 m
Asphalt surface: 5.000 square metres SMA
Poured asphalt: 570 t
Surfacing concrete: 320 cubic metres

 

 

 

Renovation of König-Karl bridge 2. BA in Bad Cannstatt

Customer: State Capital Stuttgart

Facts and figures:
Renovation: Steel bridge superstructure and track surface
260 m cantilevered parapet RHD – Covering
3,000 square metres, track surface: Sealing and poured asphalt

 

 

 

A 61 autobahn viaduct in Alzey

Customer: LBM Montabaur

Facts and figures:
- Installation of a 63 m finger plate construction
- Positioning of 2,000 shear connectors
- removal of 25 cubic metres of concrete with HDW
- Producing 40 cubic metres of concrete

 

 

 

B2 repair on western Boderle viaduct at Donauwörth

Customer: Staatliches Bauamt Augsburg

Facts and figures:
- Bridge length: 240 m
- Bridge width: 12.50 m
- Production of 200 cubic metres of surfacing concrete
- 3.000 square metres, production of bridge sealing pursuant to ZTV-ING 7.1
- 505 m new railings produced
- 505 m granite kerbstones produced
- 24 m of transition structures replaced
- 3,350 square metres of OS-B (surfacing protection system) coating on bridge visible underface
- 10 t of shotcrete produced on visible underfaces
- 2,000 square metres of mastic asphalt road surfacing

 

 

 

Repair of der B 26 Ebertbrücke in Aschaffenburg

Customer: Staatliches Bauamt Aschaffenburg

Facts and figures:
- Bridge length: 300 m
- Bridge width: 15 m
- 23,000 square metres, removal of old coating containing lead pursuant to 128
- 23,000 square metres of new priming coat and top coat on steel pursuant to ZTV-KORR Bl. 87
- 110 cubic metres of heavy concrete as ballasting support
- 600 metres, installation of new steel curbs and bridge railings
- 600 metres, removal and installation of new bridge drainage made of stainless steel
- 2,500 m, installation of new cabling for bridge lighting, etc.
- Replacement of 30 m of transition construction as well as the existing bridge support

 

 

 

A 81 autobahn FDE, Münchingen

Customer: LW/Kirchhoff consortium for RP Stuttgart Ref. 43

Facts and figures:
- Bridge length: 2 x 175 m
- Bridge width: 2 x 20 m
- Installation of 5,000 square metres of bridge sealing pursuant to ZTV-ING 7.1
- Replacement of 42 m of transition construction
- Installation of 570 t of poured asphalt 0/11 S for protective layer
- Replacement of 22 bridge drains

 

 

 

 
 