Joint venture motorway A7 renovation of road surface junction Rothenburg – border of federal land

General renovation of the federal motorway A7 on approx. 9.6 km between Rothenburg o.d. Tauber and Wörnitz

Customer: Autobahn GmbH des Bundes
Construction period: 18 months Year of construction: 2022–2023
Renovation of 4 bridge constructions
Construction of the new drainage system, 17 km transport channel and seepage water drainpipe
New construction of 270 drainage chutes
200,000 m² demolishing and processing of concrete road surface
Dismantling of protective facilities (steel) 18,000 m
Disposal of excess excavation material 100,000 t
Topsoil works: 40,000 m³ removal
Milling and removal of solidification 210,000 m²
Production of antifreeze protection layer 70,000 m³
Production of ballast base course 48,500 m³
Concrete road surface (joint venture partner Berger): 210,000 m²
Drains: slit gutters 185 pcs.
Channel crossings in reinforced concrete: 23 pcs.
Production of slit gutters 9,200 m
Tamping of existing canal with liquid soil: 4,500 m
Forest clearance: 40,000 m²

Federal motorway A8, road surface renovation Wendlingen 2019 / 2022

Lot 2 road and bridge construction

Customer: Die Autobahn GmbH des Bundes, Niederlassung Südwest
Construction period: 9 months Year of construction: 2022
3 construction phases under partial shutdown
33,500 m² demolishing of concrete road surface
5,700 t production of ballast base course
35,700 m² production of asphalt base course
35,700 m² production of asphalt binder course

Federal motorway A8, junction Stuttgart-Möhringen

Upgrade of junction 2nd construction phase

Customer: Die Autobahn GmbH des Bundes, Niederlassung Südwest
Construction period: 12 months Year of construction: 2021–2022
3 traffic phases with subsequent complete shutdown of the junction
330 m² stabilisation of building pit with soldier pile wall
360 t demolishing of building
50 m rerouting of existing canal up to 7 m of depth
3,300 m² installation of asphalt
1,800 m³ excavation of soil
42 m supporting wall (in-situ concrete & prefabricatedx parts)

Motorway BAB A81 FDE Eglosheim Ludwigsburg – FR Heilbronn

Renovation of road surface and partial enlargement

Customer: Die Autobahn GmbH des Bundes (Niederlassung Südwest)
Construction period: 10 weeks Year of construction: 2021
Renovation of about 55,000 m² surface and binder layer on a length of 3,400 m
Complete upgrade (combined antifreeze and base course 0.36 m – asphalt base course 0.22 m – asphalt binding course 0,085 m – asphalt surface layer / mastic asphalt 0.035 m) due to an enlargement of the road by 0.5 m on a length of 1,400 m at the beginning and at the end of construction works
Installation of 12,600 t asphalt binder, 0.085 m thick
Installation of 3,600 t melted asphalt, 0.035 m thick
Installation of 1,300 t asphalt surface, 0.035 m thick
Dismantling and new construction of 1,200 m slit gutter
Dismantling and new construction of 1,400 m seepage pipe
Renovation of two bridge constructions (removal and renovation of paving and sealing; repair of damaged concrete areas and joints)

Motorway BAB A3 service station with recreation area Spessart Süd

Customer: Autobahn GmbH des Bundes, ehemals Autobahndirektion Nordbayern
Construction period: 19 months Year of Construction: 2020–2021
Expansion of the service station with recreation area by 174 parking spaces for passenger cars, 132 parking spaces for trucks, 20 parking spaces for busses and caravans and several parking spaces for heavy load trucks In addition to that, the entire drainage installation, as well as all power supply facilities and lighting were newly installed. An access building to an existing supply tunnel situated below the motorway BAB A3 was also constructed.

Motorway A5 St. Leon-Rot – systematic renovation (joint venture)

Systematic renovation of motorway BAB A5 on approx. 6.6 km between interchange Walldorf and Kronau

Customer:Regierungspräsidium Karlsruhe
Construction period: 24 months Year of construction: 2019–2021
Demolition and construction of six bridge structures (direction Basel & direction Frankfurt) including widening of the undercast roads, pedestrian and cycle paths
Renovation, increase in height and extension of noise protection wall from 4 m to 8 m or from 3 m to 7 m of height
New construction of a noise protection wall of 6 m of height
Breaking up and treatment of concrete road surface 200,000 m²
Equalisation 40,000 m³
Milling of bituminous pavement 7,300 m³
Removal of protection equipment (steel) 28,000 m
Recycling / disposal 80,000 t
Removal of excess excavation material 82,000 t
Surface soil works 22,000 m³
Stone mastic asphalt – production of road surface 30,000 m²
Production of bituminous road pavement (binder, base course) 57,000 m²
Production of protective equipment (concrete) 13,500 m
Removal of solidification 180,000 m²
Production of solidification 240,000 m²
Stormwater drains road pavement 35 pcs.
Drains slit gutters 41 pcs.
Renovation of manholes 18 pcs.
Connecting lines (crossings, 41 pcs.) 1,100 m
Production of slit gutter 2,400 m
Pavement works 2,300 m²
Kerb stones 950 m

Motorway BAB A 7 Ellwangen – Virngrundtunnel Arge

Restoration and upgrade Virngrundtunnel in two construction phases (eastern and western tunnel tube)

Customer: RP Stuttgart, Außenstelle Ellwangen
Construction period: 17 months Year of construction: 2019–2020
Restoration and upgrade of concrete interior shell, as well as equipment of tunnel tubes on the basis of RABT

Milling and new construction of the 20,000 m² concrete and asphalt road surface (10,000 m² of which inside the two tunnel tubes)
Construction of a retention system for hazardous liquids consisting of disaster basin, control manhole, as well as renovation of the existing chute on a length of 200 m
Construction of a circular water supply pipe consisting of a 1,100 m long water supply system incl. two valve boxes at the two portals of the tunnel and a booster station
Installation of 12,500 t concrete, 26 cm thick
Installation of 7,500 t rolled asphalt
Installation of 1,000 m heavy duty slit gutter
Installation of 1,000 m granite kerb stones

Motorway A 8 FDE Bergwald II

Road surface renovation of three-leg interchange Karlsruhe carriageway direction Stuttgart

Customer: Regional Commission Karlsruhe
Construction period: 8 months Year of construction: 2020
4 traffic phases
24,000 m² dismantling concrete road surface, 15,000 m² dismantling asphalt road surface
39,000 m² completion (hydraulically bound base course 0.25 m, asphalt base course 0.20 m, binder course 0.085 m, stone mastic asphalt 0.035 m)
Dismantling and new construction of slit gutters 920 m
Dismantling and new construction of sewers 1,100 m
Seepage water drainpipe 5,000 m
6 bridge structures (2 new construction superstructure, 3 restoration of expansion of edge beam, 1 new surface)
Temporary release of emergency lane (underground cable engineering, foundations)
49,000 m² renovation open porous asphalt (binder course 0.08 m, sealing 0.005 m, open porous asphalt 0.045 m)