    Structure upgrade and mastic asphalt

Hamburg, A255, junction-Veddel – interchange Norderelbe, renovation surface layer

Customer: Autobahn GmbH des Bundes
Construction period: 13 months Year of construction: 2021–2022
11 construction phases, most of the time 2 construction phases simultaneously (both lanes)
approx. 120,000 m² (12,000 t) mastic asphalt surface layer removed and installed
approx. 15,000 m² asphalt binder layer produced
approx. 60 manhole covers and 450 road gullies replaced
approx. 4.5 km mastic asphalt as gutter waterway produced
approx. 27 km road marking
ca. 27 km Fahrbahnmarkierung
approx. 5.5 km steel crash barriers removed and newly installed
approx. 120 lighting masts removed

Motorway A81 road surface renovation local district Eglosheim Ludwigsburg direction HN

Customer: Die Autobahn GmbH des Bundes
Construction period: 3 months Year of construction: 2021
Installation of a mastic asphalt surface layer with a slope of up to 7 %.
approx. 40,000 m² mastic asphalt surface layer
approx. 60,000 m² binder layer
approx. 5,300 running metres mastic asphalt banquette
approx. 3,600 running metres crash barriers (renovation)

roundabout traffic Rutesheim

Customer: Stadt Leonberg
Construction period: 1 month Year of construction: 2020
Installation during moving traffic with partial shutdowns
Four Roundabouts in one month

Motorway A92 Freising

Customer: Richard Schulz Bauunternehmung / Autobahndirektion Südbayern
Construction period: 6 months Year of construction: 2019
Installation during moving traffic
Length of stretch 17 km
Mastic asphalt 9,300 t
Installation time: 2 construction phases with 6 weeks each

Stuttgart, B10 Rosensteintunnel

Customer: WOLFF & MÜLLER GmbH & Co. KG
Construction period: 11 months Year of construction: 2019
The mastic asphalt surface was grinded.
Length of tunnel 1,100 m
2 tunnel tubes
Installation by means of machines

A 70 repair of Mainbrücke bridge near Eltmann

Customer: Autobahndirektion Nordbayern
Construction period: 7 months Year of construction: 2014
14,200 m2 seal acc. to ZTV-ING 7.1
10,100 m2 protection of poured asphalt and surface layer
1,1 km drainage channels of poured asphalt

A 45 viaducts in Ambach and Windelbach

Customer: BWS Rhein-Neckar GmbH
Construction period: 15 months Year of construction: 2010–2011
19,000 m2 poured asphalt protective and surface layer on bridge constructions
11,000 m2 poured asphalt protective layer on autobahn

Zeppelinheim AS Darmstadt AK A 5 Zeppelinheim

Customer: ASV Darmstadt

5 Bauwerke instandsetzen
85 cbm Kappe abbrechen und neu betonieren
120 m Geländer erneuern
2.300 qm OS-C Beschichtung herstellen
350 qm SPCC herstellen
1.420 qm Abdichtung erneuern
200.000 qm Gussasphaltdeckschicht herstellen