High speed project Digital Control Centre Zwieseler Spinne

Pure nature and digitalisation of railway in the region Bayerischer Wald

Customer: PINTSCH GmbH
Construction period: 14 months Year of Construction: 2022–2023
In addition to the traditional underground cable works and signal foundations for the new control centre we have been awarded the contract for the simultaneous construction of railway and road, as well as for the landscape management. In connection with the project there will be further projects like the construction and foundation of five buildings for control and switchgear facilities and two hot box detection facilities. The challenges are the particularities of the pilot project, the planning legwork, the rocky ground, and the sensitive switch gear technology still in operation.
Further challenges are logistics, access ways and the delivery of material to the very remote, one-track railway line, as well as the requirements of environmental protection and species conservation.
New construction cable duct: 28,000 m
Production of track crossings: 850 m
Mounting of cable assembly chutes: 160 pcs.
Signal foundations (partly on rocky ground): 99 pcs.
Ramming of cable duct stabilisation with ballast supporting slabs: 3,600 m
Laying of cables: 288,000 m
Underground cable works for hot box detection facilities: 2 pcs.
Conversion of level crossings: 9 pcs.
Outside facilities and foundation of buildings for control and switchgear facilities: 4 pcs.
Outside facilities and foundation of buildings for control and switchgear facilities and operation building operated by traffic controller: 1 pc.

Renovation of the level crossing Posten 10

One of the busiest level crossings in Frankfurt

Customer: DB Netz AG, Frankfurt am Main
Construction period: 3 month Year of construction: 2021
Complete renovation of control, communication, and safety system, underground cable engineering, road construction, electrical engineering, telecommunication facilities and dismantling of the old barrier facility. Soil excavation of about 2,000 t and disposal, laying of cables for control, communication, and safety system 4,500 m, 15 signal foundations, 3 special foundations with 35 workers. Special challenge was the building plot situated in the inner city which was very confined, as well as the rapid execution and precise execution in a construction period of 8 weeks.

Level crossings Butzbach

Customer: Baustolz GmbH
Construction period: 1 month Year of construction: 2021
Laying of cables for control, communication, and safety
Laying of cables km 1.055 to km 1.722 + approx. 200 m in the area of level crossings
Cable duct system, underground in cable tube
Cable assembly chutes sizes IV-X: 9x size V
Signal foundations driven casing pipe: none
Signal foundations concrete monolith: 8 pcs.
Track crossings 4-12 wheel-track adhesion control in concrete: 2x as underground cable tube
Paving works, paving and asphalt
1x level crossing for pedestrians
2x level crossing for road traffic

Level crossing Kißlegg line 4560 Kißlegg - Hergatz

New level crossings for Western Allgäu

Customer: DB Netz AG, Munich
Construction period: 16 months Year of construction: September 2016–December 2017
Works carried out during train operation, creation of detailed planning, modification of the 5 existing level crossings, realisation of works during short shutdowns, 2770 m2 road adaptation, 131 km laying of cables.

Railway crossing expansion for the Bennemühlen – Walsrode Heidebahn

Faster section speed for the Heidebahn

Customer: DB Netz AG, Hannover
Construction period: 18 months Year of construction: 2011–2012
Reconstruction of 24 railway crossings
12 km of elevated cable channel
Closure of rail track crossings and provision of alternate routes
The goal was to increase the section speed from 80 to 120 km/h

Railway crossing, flashing light program, NL South-east

Major challenge in the North

Customer: DB Projektbau GmbH, Leipzig
Construction period: 36 months Year of construction: 2009–2015
Underground cable laying, cable laying, road construction, track construction, electrical engineering, telecommunications systems, coordination, execution planning. Laying of approximately 10,000 m of concrete cable duct sizes I / II, 30 pcs., cable shafts sizes IV; V and VII, rail track crossings to DN 110 to 500, complete dismantling of the crossing areas, execution within a concept of short track possessions provided by the customer with short call off times.

Railway crossing, flashing light program, NL East

Complex task in the East

Customer: DB Projektbau GmbH, Berlin
Construction period: 10 months Year of construction: 2009–2014
Underground cable laying, cable laying, road construction, track construction, electrical engineering, telecommunications systems, coordination, execution planning. Laying of approximately 9,500 m of concrete cable duct, size I / II, cable shafts, 18 pcs. sizes IV to VII, rail track crossings DN 110 to DN 400, complete dismantling of the crossing areas, execution within a concept of short track possessions provided by the customer with short call off times.