    General contractor network construction

Renovation of the level crossing Posten 10

Einer der verkehrsreichsten Bahnübergänge Frankfurts

Customer: DB Netz AG, Frankfurt am Main
Construction time: 3 month Year of construction: 2021
Complete renovation of control, communication, and safety system, underground cable engineering, road construction, electrical engineering, telecommunication facilities and dismantling of the old barrier facility. Soil excavation of about 2,000 t and disposal, laying of cables for control, communication, and safety system 4,500 m, 15 signal foundations, 3 special foundations with 35 workers. Special challenge was the building plot situated in the inner city which was very confined, as well as the rapid execution and precise execution in a construction period of 8 weeks.

Level crossings Butzbach

Customer: Baustolz GmbH
Construction time: 1 month Year of construction: 2021
Laying of cables for control, communication, and safety
Laying of cables km 1.055 to km 1.722 + approx. 200 m in the area of level crossings
Cable duct system, underground in cable tube
Cable assembly chutes sizes IV-X: 9x size V
Signal foundations driven casing pipe: none
Signal foundations concrete monolith: 8 pcs.
Track crossings 4-12 wheel-track adhesion control in concrete: 2x as underground cable tube
Paving works, paving and asphalt
1x level crossing for pedestrians
2x level crossing for road traffic

Level crossing Kißlegg line 4560 Kißlegg - Hergatz

New level crossings for Western Allgäu

Customer: DB Netz AG, Munich
Construction time: 16 months Year of construction: September 2016–December 2017
Works carried out during train operation, creation of detailed planning, modification of the 5 existing level crossings, realisation of works during short shutdowns, 2770 m2 road adaptation, 131 km laying of cables.

Railway crossing expansion for the Bennemühlen – Walsrode Heidebahn

Faster section speed for the Heidebahn

Customer: DB Netz AG, Hannover
Construction time: 18 months Year of construction: 2011–2012
Reconstruction of 24 railway crossings
12 km of elevated cable channel
Closure of rail track crossings and provision of alternate routes
The goal was to increase the section speed from 80 to 120 km/h

Railway crossing, flashing light program, NL South-east

Major challenge in the North

Customer: DB Projektbau GmbH, Leipzig
Construction time: 36 months Year of construction: 2009–2015
Underground cable laying, cable laying, road construction, track construction, electrical engineering, telecommunications systems, coordination, execution planning. Laying of approximately 10,000 m of concrete cable duct sizes I / II, 30 pcs., cable shafts sizes IV; V and VII, rail track crossings to DN 110 to 500, complete dismantling of the crossing areas, execution within a concept of short track possessions provided by the customer with short call off times.

Railway crossing, flashing light program, NL East

Complex task in the East

Customer: DB Projektbau GmbH, Berlin
Construction time: 10 months Year of construction: 2009–2014
Underground cable laying, cable laying, road construction, track construction, electrical engineering, telecommunications systems, coordination, execution planning. Laying of approximately 9,500 m of concrete cable duct, size I / II, cable shafts, 18 pcs. sizes IV to VII, rail track crossings DN 110 to DN 400, complete dismantling of the crossing areas, execution within a concept of short track possessions provided by the customer with short call off times.